To calculate operator efficiency and line efficiency in garment manufacturing, you can use the following Efficiency Formula in Garments Industry:

Efficiency Formula in Garments Industry


  1. Operator Efficiency Formula in Garments Industry.:

    Operator Efficiency (%) = (Total minutes produced / Total minutes worked) * 100

    Let's use the example provided:

    • Total minutes produced = 400 garments * 30 seconds per garment / 60 (to convert seconds to minutes) = 200 minutes
    • Total minutes worked = 8 hours * 60 minutes = 480 minutes

    Therefore, Operator Efficiency = (200 / 480) * 100 = 41.67%

  2. Line Efficiency Formula in Garments Industry. :

    Line Efficiency (%) = (Total minutes produced * 100) / (Total hours worked * 60)

    This formula calculates the efficiency of the entire production line.

    Let's say the total minutes produced by the line in a day is 12,000 minutes and the total hours worked by the line workers is 10 hours:

    • Total minutes produced = 12,000 minutes
    • Total hours worked = 10 hours * 60 minutes = 600 minutes

    Therefore, Line Efficiency = (12,000 * 100) / (600 * 60) = 33.33%

Efficiency Formula in Garments Industry. These formulas allow you to measure and track the efficiency of both individual operators and the overall production line in a garment manufacturing factory.