Efficiency Formula in Garments Industry
To calculate operator efficiency and line efficiency in garment manufacturing, you can use the following Efficiency Formula in Garments Industry:
Operator Efficiency Formula in Garments Industry.:
Operator Efficiency (%) = (Total minutes produced / Total minutes worked) * 100
Let's use the example provided:
- Total minutes produced = 400 garments * 30 seconds per garment / 60 (to convert seconds to minutes) = 200 minutes
- Total minutes worked = 8 hours * 60 minutes = 480 minutes
Therefore, Operator Efficiency = (200 / 480) * 100 = 41.67%
Line Efficiency Formula in Garments Industry. :
Line Efficiency (%) = (Total minutes produced * 100) / (Total hours worked * 60)
This formula calculates the efficiency of the entire production line.
Let's say the total minutes produced by the line in a day is 12,000 minutes and the total hours worked by the line workers is 10 hours:
- Total minutes produced = 12,000 minutes
- Total hours worked = 10 hours * 60 minutes = 600 minutes
Therefore, Line Efficiency = (12,000 * 100) / (600 * 60) = 33.33%
Efficiency Formula in Garments Industry. These formulas allow you to measure and track the efficiency of both individual operators and the overall production line in a garment manufacturing factory.