How to Calculate Overall Line Efficiency?

Calculating overall line Efficiency in a Garment Manufacturing unit involves several steps.

 How to Calculate Overall Line Efficiency in the Garments Industry?


How to Calculate Overall Line Efficiency in the Garments Industry? Here's a detailed breakdown of the process:

Step-by-Step Calculation of Overall Line Efficiency

  1. Collect Data:

    • Total Standard Minutes Produced (TSMP): This is the sum of standard minutes for all garments produced during a specific period. Standard minutes are predetermined time values assigned to each garment based on its construction and complexity.
    • Total Minutes Worked (TMW): This includes the total time worked by all operators on the production line. It encompasses both productive and non-productive times (e.g., breaks, machine downtime, rework).
  2. Formula: Overall Line Efficiency=(Total Standard Minutes Produced Total Minutes Worked)×100

  3. Calculation Example:

    • Assume you have a production line with the following data for a day:

      • Total Standard Minutes Produced (TSMP): 20,000 minutes
      • Total Minutes Worked (TMW): 25,000 minutes
    • Plug the values into the formula: Overall Line Efficiency=(20,00025,000)×100

    • Simplify the fraction and calculate the percentage: Overall Line Efficiency=0.8×100=80%

Detailed Breakdown of Key Components

  1. Total Standard Minutes Produced (TSMP):

    • This is calculated by multiplying the number of garments produced by the standard time allocated for each garment.
    • Example: If the standard time for a shirt is 30 minutes and you produced 1000 shirts, the TSMP would be: 30 minutes×1000 shirts=30,000 standard minutes
  2. Total Minutes Worked (TMW):

    • This includes all the time operators spend on the production line, both productive and non-productive.
    • Example: If you have 50 operators working 8 hours a day, the TMW would be: 50 operators×8 hours×60 minutes/hour=24,000 minutes

Factors Affecting Overall Line Efficiency

  • Machine Downtime: Time lost due to machine breakdowns or maintenance.
  • Worker Idle Time: Time when workers are not productive due to lack of work, materials, or other reasons.
  • Rework: Time spent on correcting defects or errors in garments.
  • Training and Skill Levels: Efficiency can vary based on the skill and experience of the workforce.

Improving Overall Line Efficiency

  • Process Optimization: Streamlining workflows and reducing bottlenecks.
  • Training and Development: Enhancing the skills of workers to reduce errors and increase productivity.
  • Maintenance: Regular maintenance of machines to minimize downtime.
  • Quality Control: Implementing robust quality control measures to reduce rework.

How to Calculate Overall Line Efficiency in the Garments Industry? By Regularly Monitoring and analyzing overall line Efficiency, Garment Manufacturers can identify areas for improvement and implement strategies to enhance productivity and reduce waste.